Uganda: Consortium raises capital to refinance 250-MW Bujagali hydro

A consortium of development finance institutions and commercial lenders have completed the refinancing of more than $400 million loans of Bujagali Energy Limited (BEL), aiming to help reduce electricity costs in Uganda.

The financiers include IFC, a member of the World Bank Group, African Development Bank (joint mandated lead arrangers), Netherlands Development Finance Company (FMO), France’s Proparco, Germany’s DEG, United Kingdom’s CDC and two commercial banks: ABSA and Nedbank.

The refinancing package will extend the tenor of the bulk of the senior and subordinated loans originally provided in 2007.

Bujagali, a run-of-river hydropower project on the Victoria Nile River, is one of the largest power generation plants in Uganda, contributing 45% of the country’s annual electricity generation. It provides 250 MW of clean, reliable base-load energy. Its commissioning in 2012 significantly reduced Uganda’s reliance on costlier thermal power generation.

This extension in tenor will reduce BEL’s annual debt servicing payments and make it possible for the company to reduce the cost of electricity produced by the hydropower plant over the next five years.

This was an innovative approach and one of the first to be implemented in sub-Saharan Africa in which the Ugandan government has committed to fully pass on these cost savings to consumers, in support of its goals to spur economic growth in the country.

Investors in BEL

The project has support from across the World Bank Group and the African Development Bank. As previously announced, the board of the Multilateral Investment Guarantee Agency approved political risk guarantees of up to 20 years for equity investors in BEL, helping to shore up investor support and long-term engagement with the project.

An existing partial risk guarantee from the International Development Association for two of the project’s commercial lenders remains in place.

Alongside the original financing for BEL, African Development Bank’s public sector window financed a transmission line project at Bujagali, the UECTL Bujagali Interconnection Project. The project, which links the Bujagali hydropower plant to the national electric grid, consisted of: construction of part of the Bujagali substation; construction of the Kawanda substation; extension of Mutundwe substation; social and environmental measures; consultancy services; and, financing for a Community Development Action Plan.

Bujagali’s commissioning in 2012 allowed the government to retire more than 100 MW of diesel power plants and made it possible to nearly eliminate government subsidies to the electricity sector.

Since 2005, the share of Uganda’s population with access to electricity has increased from 9% to 22%, with the total number of customers having grown from 292,000 to more than 1.1 million over the same period.

This article is shared courtesy of our partner website ESI Africa.

Previous articleHow Wind and Hydro Power Plus Energy Storage Are Paving the Way to 100 Percent Renewables in Alaska
Next articleCovanta sells 13-MW Koma Kulshan hydroelectric project to Atlantic Power Corporation

No posts to display