Vietnam seeks resettlement specialist for 156-MW Song Bung 4

Song Bung 4 Hydropower Project Management Board invites expressions of interest from consultants to serve as resettlement specialist for the 156-MW Song Bung 4 hydroelectric project in Vietnam’s Quang Nam Province. Responses are due March 23.

The Asian Development Bank is considering a proposal to provide US$196.5 million in funding for construction of Song Bung 4 on the Song Bung River. Electricity of Vietnam invited applications for pre-qualification in December 2008 to provide engineering and civil works for the project. (HydroWorld 10/16/08)

The current solicitation seeks resettlement management support over five person-months for relocation and compensation activities in four communities in the Song Bung 4 inundation area.

Song Bung 4 includes a 110-meter-tall, 367-meter-long dam with reservoir of 15.8 square kilometers, a 3.1-kilometer tunnel, and short tailrace canal.

Expressions of interest are due March 23. Work is expected to begin in April and run through September.

Expressions of interest (EOI) may be submitted via the ADB Internet site at http://csrn.adb.org:8080/csrn/publicProjectList.htm. Terms of reference are on the website.

For information, contact Tran Trung Tuyen, Song Bung 4 Hydropower Project Management Board, 5th Floor, EVN-Land Central Building, 78A Duy Tan St., Hai Chau District, Danang City, Vietnam; (84) 511-3488800; Fax: (84) 511-3621535; E-mail: tuyentt@asb4.vn.

Previous articleAlaska electric association buys 22.5-MW Terror Lake
Next articleDominican Republic seeks rehab of 52-MW Aguacate