Test operations begun at 104-MW Patuca III hydroelectric in Honduras

Honduras’ state power company Enee has begun test operations of the 104-MW Patuca III hydroelectric plant in Olancho department.

An initial 5 MW were injected into the national interconnected grid (SIN), said Enee. The plant connects to the SIN at the Juticalpa substation via a 43-km-long, 230-kV transmission line.

According to BNamericas, the powerhouse at Patuca III, on the Patuca River, contains two 52-MW Kaplan turbines. The project boasts a 57-m-high concrete gravity dam.

The Industrial and Commercial Bank of China provided financing for the US$349 million project, which was built by Chinese group Sinohydro and supervised by Consorcio Geoconsult-ACI.

Patuca III will increase Enee’s installed capacity from renewable energy to 537 MW from 433 MW, the latter of which currently accounts for nearly 17% of Honduras’ installed capacity.

Previous articleSEFA and CTF provide $25 million for independent power producers in Africa
Next articleGenex Power begins early works program for 250-MW Kidston Pumped Storage
The Hydro Review content team brings you the latest in Hydropower news. Learn about recent developments in the industry and stay knowledgeable in your field.

No posts to display