Burundi extends bidding for rehab of 18-MW Rwegura, 1.44-MW Nyemanga

Burundi’s water and electric utility has extended the deadline for bids to rehabilitate the 18-MW Rwegura and 1.44-MW Nyemanga hydroelectric projects. Bids now are due May 16.

Regie de Production et de Distribution d’Eau et d’Electricite (REGIDESO) previously called for bids by April 15. The agency also took bids in 2009 to rehabilitate Rwegura, on the Gitenge River; Nyemanga, on the Siguvyaye River; and three other small hydro projects, 850-kW Kayenzi, Kavuruga River; 240-kW Marangara, Ndurumu River; and 72-kW Sanzu, Sanzu River.

The government said it received a grant for the work from the World Bank’s International Development Association for an emergency project for the electricity sector, Projet d’Urgence pour le Secteur Electricite (PURSE).

REGIDESO said bidders may compete for either or both projects. Rehabilitation is to include mechanical, electro-mechanical, and automation equipment.

Tender documents in French may be obtained from the address below for US$100 or 120,000 Burundi francs. Payment is to be made to accounts 201-0073823-53/BIF (francs) or 201-0173824-47/USD (dollars), Banque de Credit de Bujumbura, in the name of REGIDESO/Projet d’Urgence pour le Secteur Electricite (PURSE).

Bids are due by 11 a.m. May 16. For information, contact Projet d’Urgence pour le Secteur Electricite (PURSE), Secretariat du Projet, Avenue des Travailleurs No. 22, B.P. 660, Bujumbura, Burundi; (257) 22-273246; Fax: (257) 22-273249; E-mail: dsejiji@yahoo.fr, nkurico@yahoo.fr.

For more hydropower tenders, click here.

Previous articleArchitect-engineering sought for U.S. Corps New England District