Corps extends switchgear bid date for three Ozarks hydro projects

The Corps of Engineers’ Little Rock District has extended the deadline for bids to replace switchgear and other equipment at three hydroelectric projects in the Ozark Mountains of Missouri and Arkansas. Bids now are due July 17, 2009.

Bids previously were due July 14. (HydroWorld 6/25/09) The Corps conducted site visits June 29 and 30 and July 1 at the three projects, 200-MW Table Rock on the White River in Missouri, 340-MW Bull Shoals on the White River in Arkansas, and 90-MW Norfork on the North Fork River in Arkansas.

The agency seeks bids to replace switchgear, switchboards, lighting contactors, control cabinets, motor control centers, associated controls, feeders, and conduits at the three projects.

The solicitation, No. W9127S09R0006, can be obtained from the Federal Business Opportunities Internet site, www.fbo.gov, by entering the solicitation number in the “Quick Search” box.

Bids are due by 2 p.m. July 17 to Corps of Engineers (CESWL-CT), P.O. Box 867, Little Rock, AR 77203-0867. For information, contact Brandy Thomas, Contract Specialist, (1) 501-324-5720; E-mail: brandy.n.thomas@usace.army.mil.

Authors

Previous articleU.S. sets bid date for Colorado hydro plant machine monitors
Next articleU.S. extends bid date for excitation replacement at 320-MW Fort Randall