Generating unit, crane overhauls sought for 6,809-MW Grand Coulee

The Bureau of Reclamation seeks bids for overhaul of three generating units and for crane control modifications in the Third Power Plant at the 6,809-MW Grand Coulee hydroelectric project. Bids in separate solicitations are due in October and November.

The agency recently awarded Knight Construction & Supply Inc. a US$1.5 million contract for modifications to a wheel-mounted gate servicing chamber in the Third Power Plant. (HydroWorld 8/5/10) It took bids in August to replace 15 transformers in Grand Coulee’s Left and Right Power plants. (HydroWorld 8/4/10)

The bureau seeks bids Nov. 16 for overhaul of units G-22, G-23, and G-24 at the Third Power Plant on the Columbia River, about 90 miles west of Spokane, Wash. (HydroWorld 4/26/10) The work is to include disassembling generators and turbines, overhauling and refurbishing or replacing components, and reassembling the units. The work is valued at more than $10 million.

A solicitation notice may be obtained from the Federal Business Opportunities Internet site, www.fbo.gov, by entering Solicitation No. R10PS10048 in the “Keyword/Solicitation #” box. Prospective contractors must register in the government’s Central Contractor Registration database, www.ccr.gov.

Bids are due Nov. 16. For information, contact Misty Gates, Contract Specialist, Bureau of Reclamation, Pacific Northwest Regional Office, 1150 N. Curtis Road, Suite 100, Boise, ID 83706; (1) 208-378-5079; E-mail: mgates@usbr.gov.

Crane control modifications sought for Third Power Plant

The bureau seeks bids Oct. 6 for upgrade and modernization of the control systems of six large power plant cranes in the Third Power Plant.

The cranes currently have constant-speed mechanical control systems that are to be replaced with digital variable-frequency drive control systems. The cranes include three bridge cranes, 50-ton Ederer No. 4, 270-ton Ederer No. 1, and 275-ton Ederer No. 2; and three gantry cranes, 275-ton Forebay Gantry Crane, 270-ton Draft Tube Gantry Crane, and 2,000-ton RAHCO Gantry Crane.

The work is valued at between $10 million and $25 million.

A solicitation notice may be obtained from the Federal Business Opportunities Internet site, www.fbo.gov, by entering Solicitation No. R10PS10035 in the “Keyword/Solicitation #” box. Prospective contractors must register in the government’s Central Contractor Registration database, www.ccr.gov.

Bids are due Oct. 6. For information, contact Joseph Pratt, Contracting Officer, Bureau of Reclamation, Pacific Northwest Regional Office, 1150 N. Curtis Road, Suite 100, Boise, ID 83706; (1) 208-378-5139; E-mail: jpratt@usbr.gov.

For more hydropower tenders, click here.

Previous articleNepal firm seeks partners to develop hydro project portfolio
Next articleFortis to invest in 335-MW Waneta Expansion hydro project in Canada