Transformer replacement solicited at U.S. 6,809-MW Grand Coulee

The Bureau of Reclamation seeks bids to replace 15 transformers in the Left and Right Power plants of the 6,809-MW Grand Coulee hydroelectric project. Bids are due July 28.

Reclamation has been recruiting contractors for various work to rehabilitate Grand Coulee, mainly in the project’s Third Power Plant, on the Columbia River, about 90 miles west of Spokane, Wash. (HydroWorld 4/26/10) It awarded a $26 million contract to Gardner Zemke Co. in 2009 to replace six transformers at Grand Coulee. (HydroWorld 10/19/10) Earlier that year, it awarded a $6 million contract to Koontz Electric Co. to supply three transformers at the Right Power Plant. (HydroWorld 3/23/09)

In the current solicitation, the agency seeks replacement of transformers of units G1-G9, including furnishing and installing 15 single-phase, two-winding, 13.6-kilovolt-235-kV, 50-megavolt-ampere, water-cooled transformers and appurtenances in the Left and Right Power plants.

Solicitation documents may be obtained from the Federal Business Opportunities Internet site, www.fbo.gov, by entering Solicitation No. R10PS10063 in the “Keyword/Solicitation #” box. Prospective contractors must register in the government’s Central Contractor Registration database, www.ccr.gov.

Bids are due July 28. For information, contact Susie Kramer, Contracting Officer, Bureau of Reclamation, Pacific Northwest Regional Office, 1150 N. Curtis Road, Suite 100, Boise, ID 83706; (1) 208-378-5156; E-mail: skramer@pn.usbr.gov.

For more hydropower tenders, click here.

Authors

Previous articleHydro financing consultants sought for Indus Basin in Pakistan
Next article750-MW Santa Maria hydropower project in Peru to use four Pelton turbines

No posts to display