Another new deadline for tunnel-dam work at India’s 800-MW Tawang 2

India’s NHPC Ltd. further extended the deadline for pre-qualification to construct a diversion tunnel and dam of the 800-MW Tawang 2 hydroelectric project in India’s Arunachal Pradesh State. Responses to the Lot 1 solicitation now are due October 3.

NHPC previously called for pre-qualification for two lots of civil works at Tawang 2: Lot 1 due August 30 and Lot 3, the powerhouse, due September 6. The government of Arunachal Pradesh State signed agreements in 2006 with NHPC to carry out Tawang 1 and 2, then estimated at 750 MW each.

The developer originally issued solicitations for three lots of civil works for Tawang 2. Lot 2 called for construction of a headrace tunnel.

NHPC extended the pre-qualification deadline for Tawang Stage 2:

  • Lot 1: Construction of diversion tunnel, barrage, intake, desilting chambers, silt flushing tunnels, and part of headrace tunnel up to RD 1,944 meters, completion in 65 months.

Pre-qualification documents now may be obtained until 5 p.m. October 1 for 20,000 rupees (US$375) by request labeled “Request for Pre-qualification Invitation Document for Tawang-II Lot-1 for Tawang Hydroelectric Project Stage II, 800 (4 x 200) MW.” Applications for pre-qualification now are due by 3 p.m. October 3.

Pre-qualification documents may be obtained from the NHPC Internet site, www.nhpcindia.com, for an online payment of the amounts above. They also may be obtained from the address below, with the fee paid by demand draft to NHPC Ltd. at Faridabad.

For information, contact Harish Kumar, General Manager (Civil Contracts II), NHPC Ltd., Room 215, 2nd Floor, NHPC Office Complex, Sector 33, Faridabad 121003 Haryana, India; Tel/Fax: (91) 129-2256035; E-mail: harishkumar@nhpc.nic.in; Internet: www.nhpcindia.com.

Previous articleFour small hydropower plants slated for India’s Uttar Pradesh
Next articleCorps Hydroelectric Design Center to seek management study