Eighth unit operating at RusHydro’s 3,000-MW Boguchanskaya hydropower plant

RusHydro Logo

The eighth hydroelectric generating unit at JSC RusHydro’s Boguchanskaya plant began operating Dec. 30.

This brings total installed capacity of all operating units to 1,998 MW, with a working capacity based on reservoir level of 1,362 MW.

The first seven 333-MW units were put into operation during 2012 and 2013. Preparation of the final unit for testing is currently under way. Each unit was manufactured by Power Machines at a cost of US$117.3 million.

From January to November 2013, the Boguchanskaya powerhouse supplied 4,367 GW of electricity to the wholesale and capacity market, RusHydro (LSE: HYDR) says.

Development of Boguchanskaya, on the Angara River in the northern part of Russia’s Krasnoyarsk Region, is a 50/50 joint venture of RusHydro and Russian aluminum company UC RUSAL.