European bank funds 5.1-MW Cerruje 1, 2 in Albania

TIRANA, Albania 12/5/11 (PennWell) — The European Bank for Reconstruction and Development (EBRD) has approved a 3 million euro (US$3.9 million) loan to finance construction of the 5.1-MW Cerruje 1 and 2 hydroelectric projects on Albania’s Benji River.

EBRD made the loan to an Albanian private developer, Energy Partners, under the bank’s Western Balkans Sustainable Energy Direct Financing Facility.

Energy Partners is to build the two hydro plants 140 kilometers northeast of Tirana. They are to generate up to 14.7 gigawatt-hours annually, helping to offset generation of 9,500 tons of carbon dioxide by other power plants.

Energy Partners plans to develop a total of five hydro plants on the Benji, for which the company received a 35-year concession.

“The construction of the Cerruje hydropower plants is one of the few private investments in renewable energy generation in Albania in many years,” Fabio Serri, head of EBRD’s Albania office, said. “This project will be implemented with the support of latest technologies and will set an excellent example of financially viable investments in renewable energy sector.”

Previous articleDraft U.S. study endorses dam safety work at 3.65-MW Stampede Dam
Next articleWashington tribe advances fish restoration work at Elwha and Glines Canyon dams

European bank funds expanding three Spain pumped-storage plants

The European Investment Bank (EIB) is lending 300 million euros (US$448.7 million) to Spanish utility Iberdrola to help finance three pumped-storage projects as expansions of existing hydro plants.

Officials of the European Union’s bank and the hydropower operator signed an agreement November 13, 2009, to finance half the estimated 600 million euro (US$896.7 million) cost of the 177-MW San Esteban 2 and 25-MW San Pedro 2 projects on the Sil River in Ourense Province and the 852-MW La Muela 2 project on the Jucar River in Valencia Province.

“In line with the EU energy policy, the EIB supports projects meeting the threefold objective of increasing energy efficiency, improving the security of supply, and fostering clean energy,” EIB Vice President Carlos da Silva Costa said.

Iberdrola has been expanding existing hydroelectric projects for pumped storage to support the development of intermittent renewables generation such as wind power. (HRW June 2009) The existing projects are 263-MW San Esteban, 33-MW San Pedro, and 635-MW La Muela.

Iberdrola is expected to issue solicitations for equipment and civil works under EIB procurement rules. The investment mainly concerns electro-mechanical equipment such as turbine-generators and transformers and underground civil works such as water intakes, penstock tunnels, and powerhouse caverns. None of the work would enlarge dams or transmission lines or increase inundation.

In August, Voith Hydro announced it received a US$34.1 million contract to supply a Francis turbine, vertical generator, and 32-meter-long steel liner for San Esteban 2. (HydroWorld 8/19/09) In 2008, Iberdrola awarded a US$57.3 million contract to Voith to supply four pump-turbines and spherical valves for La Muela 2. (HydroWorld 7/15/08)