Qualifying dates extended to build India’s 520-MW Teesta 4

FARIDABAD, India 6/7/12 (PennWell) — India’s NHPC Ltd. has extended the deadlines for pre-qualification to construct two lots of civil works of the 520-MW Teesta Stage 4 hydroelectric project in India’s Sikkim State. Responses to two solicitations now are due June 29 and July 3.

NHPC previously invited applications for pre-qualification for the work by June 1 and 5.

Sikkim’s Energy and Power Department signed agreements with NHPC in in 2006 providing for development of Teesta 4 and the 210-MW Lachen project on a build-own-operate-maintain basis. Teesta 4 is one of six hydropower projects proposed for a cascade on the Teesta River. The project is to feature four 130-MW turbine-generators.

NHPC issued two solicitations for civil works of Teesta Stage 4: 
Lot 1: Construction of diversion tunnels, coffer dams, concrete gravity dam, intake, spillway, diversion tunnel gates and hoist, desilting chambers, and headrace tunnel up to RD 1,780 meters, completion in 67 months.

Pre-qualification documents now may be obtained until July 2 for 40,000 rupees (US$742) by request labeled “Request for Pre-qualification Invitation Document for Lot 1 for Teesta HE Project (Stage IV).” Applications for pre-qualification now are due by 2 p.m. July 3. 

Lot 2: Construction of headrace tunnels from RD 1,780 meters onward, adit 2, surge shafts, pressure shafts, underground powerhouse, transformers hall, tailrace tunnels, and pothead yard, completion in 60 months.

Pre-qualification documents now may be obtained until June 28 for 20,000 rupees (US$371) by request labeled “Request for Pre-qualification Invitation Document for Lot 2 for Teesta HE Project (Stage IV).” Applications for pre-qualification now are due by 2 p.m. June 29.

Pre-qualification documents may be obtained from the NHPC Internet site, www.nhpcindia.com, for an online payment of the amounts above. They also may be obtained from the address below, with the fee paid by demand draft to NHPC Ltd. at Faridabad.

For information, contact A.K. Pathak, Chief Engineer (Civil Contracts VI), NHPC Ltd., Contracts Civil Division, 2nd Floor, NHPC Office Complex, Sector 33, Faridabad 121003 Haryana, India; (91) 129-2259925; Fax: (91) 129-2274004; E-mail: ak.pathak@nhpc.nic.in; Internet: www.nhpcindia.com.

Previous articleU.S. seeks chains for submersible barrier screens at 980-MW McNary
Next articleFERC OKs Lake of the Ozarks boundary redraw, ending encroachments

No posts to display