Russia’s HydroOGK seeks turbines for 2,541-MW Volzhskaya

Russian hydropower generator HydroOGK invites applications for pre-qualification to supply four replacement turbines for rehabilitation of the 2,541-MW Volzhskaya hydroelectric project. Responses are due June 26.

With 6.3 billion rubles (US$233.5 million) in funding from the European Bank for Reconstruction and Development (EBRD), HydroOGK plans to seek bids for turbine-generators and switchgear for rehabilitation of plants in the 10,000-MW Volga-Kama hydropower cascade, including Volzhskaya. (HNN 7/20/07) The utility previously invited pre-qualification by May 29 to supply three replacement turbines for the 458-MW Kamskaya project. (HNN 4/30/08)

In the current solicitation, the tender organizer, CJSC Energoservis-Konkurs, seeks to pre-qualify bidders to design, supply, and install replacement turbines for Units 12, 5, 21, and 20 of Volzhskaya. Work is scheduled on Unit 12, December 2008-March 2010; Unit 5, April 2009-March 2011; Unit 21, August 2009-October 2011; and Unit 20, April 2010-May 2012.

Pre-qualification documents may be obtained from the address below by written request including name of prospective bidder, subject of procurement, form of documents delivery (e-mail, courier, at organizer’s office), and contact information.

Pre-qualification applications are due by noon June 26. For information, contact Camilla Salakhova, CJSC Energoservis-Konkurs, Vernadsky Prospect, Bld 93/1, Room 220, Moscow 119526 Russian Federation; (7) 495-4346113; Fax: (7) 495-4345074; E-mail: salakhova@tenderenergo.ru.