U.S. again extends call to replace fire-damaged electrical equipment at 1,125-MW Grand Coulee Right Power Plant

The Bureau of Reclamation again extended the deadline for bids to replace fire-damaged electrical equipment at the 1,125-MW Grand Coulee Right Power Plant in Washington. Bids now are due Jan. 6, 2014.

Reclamation previously called for bids by Dec. 30 and 23. 

The Right Power Plant is a development of the 6,809-MW Grand Coulee hydroelectric project on the Columbia River.  Other developments are the 1,155-MW Left Power Plant, the 4,215-MWThird Power Plant , and the 314-MW John W. Keys III Pump-Generating Plant

In a solicitation set aside for small businesses, Reclamation now seeks bids for isophase bus replacement for Unit G10 of the Right Power Plant, including removal of the existing isophase bus and associated generator surge arrestors and capacitors, and supply and installation of three new phases of isolated phase bus between G10 generator and K10A transformers and associated generator surge arrestors and capacitors. Work also includes repair of any conduits and circuits in the immediate vicinity of the recent electrical fire.

The work is valued at $1 million to $5 million.

A solicitation notice may be obtained from the Federal Business Opportunities Internet site,www.fbo.gov, by entering Solicitation No. R14PS10001 in the “Keyword/Solicitation #” box. 

Bids now are due Jan. 6. For information, contact Susie Kramer, Contracting Officer, Bureau of Reclamation, Pacific Northwest Regional Office, 1150 N. Curtis Road, Suite 100, Boise, ID 83706; (1) 208-378-5156; E-mail: skramer@usbr.gov.

Previous articleVoith Hydro names new director of marketing and sales
Next articleFERC receives six hydro license applications totaling 43.825 MW