U.S. again extends date for switchyard circuit breakers at 600-MW Richard B. Russell pumped-storage

The U.S. Army Corps of Engineers again extended the deadline for bids to install replacement circuit breakers and to refurbish the switchyard of the 600-MW Richard B. Russell pumped-storage project on the Savannah River in Georgia. Bids now are due Aug. 8.

The Corps’ Savannah District previously called for bids by Aug. 1 and July 9. The Corps recently received permission to operate all four of Russell’s reversible pump-turbines after a decade of environmental litigation. The plant has four 75-MW pump-turbines and four 75-MW conventional units.

The Savannah District awarded a contract in 2012 to Atlantic Electric LLC to replace main unit breakers and static excitation systems and to install a static frequency converter system at the hydroelectric project. It also named HDR Engineering Inc., to evaluate operating practices of Russell, and the 422-MW Hartwell and 280-MW J. Strom Thurmond hydroelectric plants, also on the Savannah.

In a solicitation set aside for small business, the Corps now seeks installation of government-furnished circuit breakers to replace 25-year-old oil-filled units at the switchyard adjacent to the Russell project. Work also is to include removal of old circuit breakers and oil storage tanks, modifications to bus work and cabling, and related work.

A solicitation notice may be obtained from the Federal Business Opportunities Internet site, www.fbo.gov, by entering solicitation No. W912HN13R0003 in the “Keyword/Solicitation #” box.

Bids now are due at noon, Eastern time, Aug. 8. For information, contact Nikisha V. Weston, U.S. Army Corps of Engineers District, Savannah, Attn.: CESAS-CT, P.O. Box 889, Savannah, GA 31402-0889; (1) 912-652-5102; E-mail: nikisha.weston@usace.army.mil.

Previous articleU.S. House committee approves additional small conduit hydro development bill
Next articleBill introduced to aid American marine hydrokinetic industry