UPDATE – India’s NHPC sets new date for six-plant SCADA system

India’s National Hydroelectric Power Corp. (NHPC) has extended the deadline for pre-qualification applications to supply automation and supervisory control and data acquisition (SCADA) equipment for six hydroelectric projects.

The application deadline is extended to December 5 from October 31. (HNN 9/19/07)

NHPC plans to seek proposals to supply, install, and commission automation and SCADA equipment at the 180-MW Baira Siul (HNN 6/10/05), 105-MW Loktak (HNN 7/12/06), 690-MW Salal (HNN 3/2/06), 540-MW Chamera 1, 120-MW Tanakpur (in Nepal) (HNN 7/4/06), and 60-MW Rangit (HNN 3/20/06) projects. It also seeks a mimic display system at the NHPC corporate office in Faridabad.

NHPC issued a similar request in 2006 for a SCADA system to link the six projects, plus the 400-MW Uri project.

The deadline for obtaining pre-qualification documents from NHPC’s Internet site, www.nhpcindia.com, also was extended to November 19. Those who do so must submit a letter of confirmation by November 26 to the address below with a document fee of 5,000 rupees or US$125 in the form of a crossed demand draft to National Hydroelectric Power Corp. Ltd. at Faridabad. The documents also may be obtained in person or by mail until November 19 from the address below for the same fee.

Applications for pre-qualification are due by 2 p.m. December 5 to the address below. For information, contact J.R. Chaudhary, Chief Engineer (E), Contracts (E&M)-III, National Hydroelectric Power Corp. Ltd., 2nd Floor, NHPC Office Complex, Sector 33, Faridabad, Haryana 121003 India; Tel/Fax: (91) 129-2259920, 129-2255952; E-mail: jrchaudhary@nhpc.nic.in; Internet: www.nhpcindia.com.

Previous articleNorway generator pre-qualifies equipment suppliers
Next articleApplying Models to Determine Sediment Transport in Rivers